- Nanotechnology Cleanroom Design ConsiderationsScott Mackler and Tim Loughran Presented at Weizmann Institute of Science
Case Study: Cambrex Biosciences Process Development Lab Expansion
In the Summer of 2002, Cambrex Bio Science Baltimore, Inc. commissioned a 3rd Party engineering firm to develop a Basis of Design (BOD) document for the 30,000 ft2 expansion of their process development laboratories at their Baltimore facility. The expansion consisted of 9,000 ft2 for offices, 13,000 ft2 of laboratory area, and 8,000 ft2 of mechanical support space, located within an existing warehouse building adjacent to their manufacturing plant.
The Challenge
In the Summer of 2002, Cambrex Bio Science Baltimore, Inc. commissioned a 3rd Party engineering firm to develop a Basis of Design (BOD) document for the 30,000 ft2 expansion of their process development laboratories at their Baltimore facility. The expansion consisted of 9,000 ft2 for offices, 13,000 ft2 of laboratory area, and 8,000 ft2 of mechanical support space, located within an existing warehouse building adjacent to their manufacturing plant. However, the project’s preliminary needs and budget did not match. The budget required a nearly 30% reduction at a total savings of nearly $1.5 million, yet the user group could not sacrifice any of the preliminary requirements of the BOD.
Michael Wisler, Cambrex’s Director of Engineering Services, decided to take a unique approach to delivering the project. Utilizing the BOD as the basis of a request for proposal (RFP) and as a starting point to deliver the intent of the facility design, Wisler solicited design-build proposals from several teams. Within the RFP was the requirement to propose value engineering alternates to meet the user requirements and the target budget of $4.2 million.
Susan Boggs, of Turner Construction Company’s Mid-Atlantic Region, teamed with AdvanceTEC, a firm specializing in delivery of design-build cleanrooms and laboratories, to assemble a project team that focused on a deliverable that met the intent of the BOD without sacrificing space, functionality, or the Cambrex budget. Wisler’s evaluation team interviewed all proposing teams and selected the Turner team–the group that presented the most innovative approach to achieving Cambrex’s desired facility and further, the team that displayed the most flexibility in working openly with the client to achieve their goal while maximizing their investment.
Design Modifications
Once the project team was assembled, they set out to value-engineer the facility design, without downgrading functionality, while keeping in focus the eight-month project duration mandated by Cambrex management. The design team, led by Frank Haughey of Turner Construction and John Burton of AdvanceTEC, re-evaluated the utility and redundancy requirements to maximize savings. The results of the evaluation yielded a $1.5 million savings; redundancy was considered a luxury that the project could not afford.
The first major savings was incurred through the decision to change the HVAC in the administrative areas from a chilled water design to a direct expansion unit. While operating costs would increase slightly, the change allowed for the downsizing of both the plant steam and chilled water systems, as well as allowing for the optimum placement of the unit, thus reducing the installation and duct costs. Additionally, during the procurement process, a pre-packaged HVAC unit meeting the Cambrex Project capacity requirements (ordered for another area project but never utilized) was purchased. As a result, the cost of the unit was $20,000 less than the price of a new one. All told, this change netted a $250,000 savings from the original budget.
Now that the HVAC for the lab areas were going to operate independently from the administrative spaces, the lab HVAC could be redesigned as well. The concept of a central HVAC mezzanine for all systems was revised and replaced with a floor-mounted system in the mechanical space. Additionally, the concept of a central air handling unit and elaborate duct distribution system with VAV boxes for individual labs was replaced by a system utilizing a central make-up air handler and individual modular climate changers serving each lab independently. This design resulted in the individual labs utilizing the same amount of control points, thus maintaining the functionality, and afforded the labs individual operation with significantly less ducting and a more evenly distributed structural loading. The more evenly distributed loading afforded a structural reinforcement budget savings of over $100,000.00.
In conjunction with the downsizing of the plant steam system, the method of generation was re-evaluated. The original design included a system operating using natural gas. However, the existing warehouse building had no gas supply and the nearest main was located approximately 1,000 feet away. A cost analysis revealed that the use of an electric boiler would increase annual operating costs by < $10,000. This was justified by the $20,000 in savings on the purchase of an electric unit versus a gas-fired one as well as the $500,000 that was saved on the installation of a dedicated gas service.
Once the systems had been sized, the design team attacked the lab layout to achieve more economical routing of air and pipe systems. Again, the intent of the BOD and process flow was not compromised. Wet services were moved together within the lab layout to utilize common utility delivery chases and minimize service runs. This change affected the deionized (DI) water system, plant and clean steam, compressed dry air, process chilled water and the process gases (O2, N2, and CO2). The internal layouts of the labs were re-programmed to minimize the amount of underground existing in-slab piping. The resultant effect was a savings of 150 linear feet of floor drains, with the associated slab cutting and patching, and a reduction of the utility delivery service of nearly 2,000 linear feet. These changes contributed a savings of nearly $250,000.00 to the project budget.
An additional 20-25 smaller items were evaluated. Of those approximately 10-15 were deemed feasible and were implemented. An additional $100,000 – $150,000 was realized through these miscellaneous items.
The design changes alone left the team $400,000 short on the goal of $1.5 million in savings. The Cambrex engineering staff set out to achieve the final goal. Roy Schnebelen, Cambrex’s project manger assembled the user group and Design/Build team to re-evaluate facility finishes and specifications. After further discussions with the user group, several material specification and finish detail requirements were revised to meet the target budget. The DI water system loop piping was further evaluated and determined not to require stainless steel piping. Polypropylene piping was substituted, which met all requirements of the users. Flooring within the laboratories was revised from seamless vinyl to rolled on 40 mil epoxy (see Photo 1). The design/build team searched the surplus equipment market and identified a reconditioned autoclave for the project, which allowed for the transfer of $100,000 from the equipment to the construction budget. Finally, the size of the glassware washer was re-evaluated and reduced at a savings of $40,000.
Schedule Coordination
While the design team was carrying out the extensive value engineering process, the construction team was charged with creating a construction schedule that maintained the overall eight month duration of the project, while absorbing the impact of a four week design schedule requiring eight weeks. The construction team, comprised of Roy Schnebelen of Cambrex, Roy Revis of Turner Construction, and Koray Ozgenc of AdvanceTEC created a detailed construction sequence that anticipated and communicated staged deliverables from the design team and allowed for the overall extension of the design process while shortening the construction schedule to meet the original expected completion date.
There were two key factors in shortening the construction schedule: 1) The elimination of the required structural modifications to the existing building, and 2) The use of modular wall systems instead of a standard stick-built approach. The elimination of the structural support system required mounting of items previously designated as roof mounted equipment to be set on the perimeter ground, thus allowing for earlier installation and tie-ins. The use of modular wall systems allowed for factory fabrication concurrent with preliminary site work. It also significantly decreased the requirements for on-site interior finish systems. These two items provided enough time savings to more than make up the additional time spent in design.
Cambrex’s commitment to the schedule was imperative to the success of this team process. Early on, the Cambrex engineering team insisted that lab cards be re-developed to insure the revised systems’ design were appropriate and accurate. The user group participated in the review of the lab cards, to achieve buy-in across the board throughout their organization. A design cut off date was established and communicated to all members of the process. The date was published and highlighted within the schedule to insure all parties were aware of it. No design changes were entertained after the cut off date. This regimented process insured researchers were available and participated in the lab card review meetings when they were scheduled.
The key factor in shortening the construction schedule was the elimination of anticipated structural modifications to the existing building that were eliminated once detailed investigation of the existing structure was completed and the design concept was modified to a modular type design. This concept allowed for factory fabrication of wall panels while preliminary site work was being performed, and significantly reduced site finish work resulting in a one month reduction in the site construction duration. In addition, the mechanical delivery systems were downsized, and the roof mounted equipment was relocated to perimeter ground once the floor plan was reoriented within the building to allow for proper process flow and access.
The aggressive schedule dictated that the construction team pre-purchase all long lead equipment while the detailed design drawings were being completed. Once the subcontractors were selected the long lead items were assigned to the appropriate trades for receipt and coordination. Subcontractor bid packages were released in conjunction with the construction sequence while plumbing and HVAC packages were broken into smaller pieces such as drains, plumbing, hi-purity process, HVAC ducting, and exhaust systems. This modular approach afforded the design team additional time, where required, and still allowed the construction team to maintain the bid schedule. All bidders were interviewed (with mandatory attendance by a principal of the proposing firm) to assist in identification of scope gaps and/or misinterpretation of their required scope of work. These interviews were also used to review the schedule requirements of the contract and receive commitment from key members of the subcontractors’ organizations. A detailed comparison spreadsheet was developed for each bid package and the entire project team reviewed the comparisons and selected the subcontractors. The result: Less than 1% change orders, including requested scope changes by the owner, on the project from award to project close out.
Construction
Once construction began, the construction team worked pro-actively to ensure the schedule was maintained. Turner and AdvanceTEC’s site superintendents, Roy Revis and Steve Mart, met daily with the owner to update work activities. Progress was tracked on the site drawings, color coded by day, and cross-referenced to the construction schedule. When construction issues surfaced, the superintendents were charged with assembling a representative from Cambrex, Turner, and AdvanceTEC to review the issue and provide a solution to the team. Decisions were made expeditiously, and the team moved forward.
The construction schedule was updated and published weekly by Turner and AdvanceTEC, and reviewed in their weekly site subcontractor meeting. Critical period’s required detailed sub-schedules which for some tasks (factory start up and training for example) required hourly breakdowns to insure coordination issues did not produce unproductive time for team members. When subcontractors were not on schedule, the construction team evaluated man loading and adjusted appropriately. A weekly owner’s meeting was held to update the Cambrex staff and discuss critical path issues.
The Results
The project team’s commitment to their structured client-focused process for providing a high quality finished product that met the user’s needs, resulted in a project that was delivered on schedule, under budget, and with less that 1% change orders. The construction team’s zero punch list approach resulted in project close-out and sign-off within 2 weeks of substantial completion. The project was completed in May 2003, and to date, the team has discovered only one minor missed requirement, which was promptly resolved. As in all projects the team members agree that there is always room for improvement; however, as a group, the Cambrex Staff is quite pleased with the resultant facility and the value of the project..