Iberian National Laboratory (INL) Braga, Portugal
CONTRACT VALUE: Consultant to HDR Inc.
CLASSIFICATION: 10/100/1000
SCOPE: Design Review/Product & Equipment Specification/Constructability Review/Value Engineering/Build Clean Protocol Development/Construction QA/QC
DESCRIPTION: Contracted to the Construction Manager and the request of the Designer and Owner to review cleanroom submittals and comment on budgets, schedules, sequence of construction, protocol, and material and equipment alternatives. Developed the cleanroom construction sequence, schedule, and build clean protocol. Trained Construction Manager’s personnel on monitoring and implementing the build clean protocol
COMPLETED: 2010
INDUSTRY: Microelectronics, Nanotech, Research